NPG has been hired to complete the seal coat and stripe on the following streets: Birdie, Amateur (upper part), Hosel, Bowker Play, Divot, Gallery (upper part), Wedges, Deuce, Zillion and Mulligan.

Please note that water needs to be shut off 48 hours prior to the seal coat project and needs to stay off 48 hours after the street is opened. Any water that goes onto the street prior and during the seal coat will cause the seal not to properly adhere to the asphalt for which you may be held financially responsible for repairing.

The schedule will be as follows:

Sweep Community:        Tuesday 9/22/20

                Post Notices (Ph 1 & 2): Friday 9/25/20

                Phase 1, Seal & Stripe:   Monday 9/28/20

                Phase 2, Seal & Stripe:   Tuesday 9/29/20

                Post Notices (Ph 3 & 4): Friday 10/2/20

                Phase 3, Seal & Stripe:   Monday 10/5/20

                Phase 4, Seal & Stripe:   Tuesday 10/6/20

Work Hours:                     7:00am to 5:00pm

Schedule above is weather permitting. Please make sure all work areas are clear from vehicles, pallets, etc., before the crew arrives. 


Notices
and maps will be posted on your garages prior to your street being worked on. Please contact management should you have any questions. 

Location

13160 Balata Street
Beaumont, CA 92223

Management Team

Community Manager
Valerie Raboin | vraboin@actionlife.com

Manager Assistant
Katie Greer | kgreer@actionlife.com

Management Company

Action Property Management
www.actionlife.com
Regional Office
1250 Corona Pointe Ct, Suite 404
Corona, CA 92879
phone | (949) 450-0202
fax | (951) 272-0720

Corporate Office
2603 Main Street, Suite 500
Irvine, CA 92614
phone | (949) 450-0202
fax | (949) 450-0303